Project Number:
2023-2025 Hwy 7
Rehabilitation of bridge structures on Hwy 7 at Silver Creek and Credit River
The scope of this project at both sites on Hwy 7 includes, but is not limited to:
• Two bridge rehabilitations;
• Environmental protection, landscaping, erosion and sediment control;
• Drainage and stormwater management;
• Traffic staging and traffic management.
2023-2012 Hwy 10
Rehabilitation of culverts on Hwy 10 at Snelgrove Creek and Etobicoke Creek
The scope of this project at both sites on Hwy 10 includes, but is not limited to:
• Two culvert rehabilitations;
• Environmental protection, landscaping, erosion and sediment control;
• Drainage and stormwater management;
• Traffic staging and traffic management.
Please note:
Closing date for contract 2023-2025 is October 31, 2024 (2172-16-00)
and closing date for contract 2023-2012 is December 31, 2023. (2372-15-00)